ON2744 Finning UK Ltd

This project was a very interesting hybrid two tier mezzanine floor with integrated racking on the one side where we added walkways.

Method:
For this project we used one counterbalance fork lift truck with two electric scissor lift the main steel work was installed working from the back to the front, next the deckbeams were installed using the scissor lifts, then the decking was installed on each level starting on the mezzanine floor and then laying on the walkways, then the twin flight stair tower was installed.

We found out just before we started the project that the weather was going to be a bitter -5 we heard that the delivery vehicle had problems prior to arriving on site as well as the hire equipment delivery vehicle, but all companies made it in good time and in a safe manner we lost a morning but better to be safe.

As far a projects go this one was definitely different but again a pleasure to work on.

Summary:
We constructed the mezzanine floor steelwork in one, then installed the 38mm decking with the twin flight staircase on the side, no issues during the build even though the weather was against deliveries and hire equipment in the -5 degrees.

Facts:

  • Build Time: 5 days
  • Labour: 2-person
  • Size: 6.75M x 6.6M x 5.20M
  • Location: CF72 8LX

Moor Storage Ltd, Second Floor, Cranham House, 136 High Street, Amblecote, Stourbridge DY8 4BU